Construction report for the Alpha Range:

Everyday now on site allows for items on the punch list to be scratched off and noticeable finishing progress made.  
ComEd completed the 3-phase installation on the pole and feed to the building, and our new panel is now hot with the step down transformer running (huge!).  Track lights are going up and outlets are hot.  Paint is done.  Bathroom tile work is done.  Trim is underway.  And then there are 4 guys from Provo setting up some impressive looking steel at the south end of the building...   
Within two weeks I’m gonna have a will power test to keep from sneaking a few early rounds down range!

I'm super excited - a Pine Tree-like facility in the area! Can't wait!